"The docks were developed in 1974 and have reached the end of their useful life." That line comes from the City of Mercer Island's project FAQ. The next sentence explains the timing. Docks that fall into disrepair "can be declared 'derelict' and no longer eligible for repair or replacement permits."
So the waterfront at Luther Burbank Park is being rebuilt while the city can still get a permit to rebuild it. That is why planning began in 2014, and it is why construction is now about to take a share of the park for well over a year. For anyone who walks the north end, launches a kayak from the park, or brings guests to North Beach, the city has not yet said which part of the park will close.
A deadline set by permit rules
The city's own explanation ties this schedule to permits. If a dock is allowed to decline far enough, the option to repair or replace it can be lost. The city calls the docks "developed in 1974" and still in use, which makes them 52 years old this year, and planning started twelve years ago for that reason.
The steps from there, as the city describes them:
- 2014. The city begins planning for the future of the docks.
- 2019. Work starts on the current project, guided by the 2006 Luther Burbank Park Master Plan. That plan describes the waterfront as a hub for small motorized and hand-powered watercraft.
- 2020 and 2021. Public input shapes the improvements, together with the Mercer Island Parks and Recreation Commission.
- 2021. Interim dock repairs keep the structures usable while design continues.
- March 2022. City Council approves the Commission's recommended 30% design.
- 2024. Seismic retrofits and other improvements are finished on the Boiler Building and the restroom and concession stand annex.
- August 2026. Final design and permitting are complete.
- September 1, 2026. Council awards the construction contract on its consent agenda.
The 2021 repairs are the step most people would miss. They bought time so the docks would not slide toward "derelict" status while the permanent design moved through the process. The 2024 Boiler Building work was handled separately, and this fall's contract covers the docks, North Beach, and the waterfront plaza.
Who is building it, and who is paying
The contract went to Quigg Bros., Inc., an Aberdeen-based marine construction firm. According to the city's project news feed, its recent waterfront work includes the Des Moines Marina Redevelopment in 2025 and 2026, the Port of Poulsbo Breakwater Replacement from 2022 to 2024, and several Foss Waterway projects for the City of Tacoma. The construction contract is $6,730,000 including sales tax.
The city reports more than $5 million in local, state, and federal grants secured for design, permitting, and construction. The named funders are the Washington State Recreation and Conservation Funding Board, the U.S. Department of Fish and Wildlife, and the King County Flood Control District. According to the project page, the Washington State Department of Natural Resources leases the shorelands at no cost for public access to the waters of the state.
What the waterfront looks like when the fences come down
The city's project page lists the scope in detail. The parts that change how the park is used:
| Element | What changes | Who it serves |
|---|---|---|
| North pier | Renovated: new decking, creosote-timber piles jacketed, failing piles repaired or replaced | Moorage for motorized boats 26 feet and longer |
| Central and south docks | Replaced with a new wave attenuator and mooring float | Motorized boats under 26 feet |
| Special purpose float | New, with an ADA-accessible kayak launch | Non-motorized watercraft |
| Overwater platform | New ADA platform off the plaza bulkhead | Visitors who want to "get their feet wet" |
| North Beach | New concrete path from the north bulkhead, ADA beach mat to the water, native plantings in place of non-native vegetation | Swimmers and beachgoers |
| Plaza to playground | The existing hidden path becomes an ADA switchback trail with concrete stairs | Families moving between the waterfront and the playground |
| Plaza | New surfacing, picnic tables and benches, signage, and the Mercer Island Medallions public art project | Everyone |
Some of the work happens out of sight. The project adds ADA path connections from the South Shoreline Trail and places habitat gravel along the shoreline as part of a lakebed cleanup. It upgrades sewer, electrical, stormwater, and irrigation utilities, and it installs a new fire suppression system for the docks and the Boiler Building.
It also installs a raw water intake so the city can activate its water rights and draw from Lake Washington to irrigate the park. Once that is running, the lawns in a lakeside park can be watered from the lake.
The table also shows a design choice. The new layout separates boats by size and puts paddlers on their own float. That follows the 2006 master plan's description of this shoreline as a watercraft hub, for small motorized boats and for kayaks and paddleboards alike.
The calendar math puts summer 2027 inside the window
The city expects construction to begin in fall 2026 and take 15 to 18 months. Counting from a fall 2026 start, that runs into the first half of 2028. The project tracker labels the construction stage "2026-2027," and as of its October 9 update it shows the project at that stage. Either way, the whole summer of 2027 falls inside the construction period.
That matters because several items in the table above are the park's summer draws: North Beach, the docks, the moorage, and the plaza. All of them are in the project scope. The city has not said which of them will be fenced off at any given time. Its August 28 notice says this:
"During construction, a portion of Luther Burbank Park will be closed to support construction activities and ensure public safety. The remainder of the park will remain open to the public throughout construction. Additional information about specific closures and impacts will be shared as construction progresses."
The September 3 Parks and Recreation Commission packet repeats this. It says portions of the park will be closed throughout construction and that updates will be shared once work begins. The city has not published a closure map, a staging area, or a firm start date. The project page says closure information will be posted on Let's Talk "once work begins."
Of all the park's features, the city has named only the waterfront itself as affected. Whether the off-leash area, the playground, the trails, or other spots away from the shoreline are touched will depend on where the contractor sets up. The city has said it will publish that information, but it has not done so yet.
The best way to track it is the project page at letstalk.mercergov.org/lbdock. The city says regular updates will be posted there once construction starts.
Other public water access on the city's list
While the Luther Burbank shoreline is partly closed, the city's beaches page lists other public access points on the island. The city has not named any of them as stand-ins for this project. These are simply the sites it already maintains:
- Calkins Landing, at SE 28th Street and 60th Avenue SE. This is the north-end option on the list, a developed street end with waterfront access and an accessible picnic area.
- Groveland Beach Park, at SE 58th Street and 80th Avenue SE, listed as a swimming beach.
- Clarke Beach Park, at East Mercer Way and SE 77th Place, with an enclosed swim area and piers.
Groveland and Clarke are much farther south than Luther Burbank. For a north-end household, the summer 2027 beach day may mean a longer drive. Calkins Landing is the closest of the three, but it is a street end and not a full beach park.
Getting to the park this week
Some north-end residents reach the park on foot from Mercer Island Station, which opened for 2 Line service on March 28, 2026. Sound Transit's station page notes sidewalk work at the west entrance on 77th Ave SE through Saturday, October 31. During work hours, the north-side sidewalk and the drop-off and pick-up area are closed, and the entrance can be reached only from the south. Families heading to Town Center Trick-or-Treat on Friday, October 30, from 4 to 6 p.m., will find Island Books, Mioposto, Pagliacci, and other businesses taking part, according to the city's event listing.
If you own a home near Luther Burbank and are thinking about a sale sometime in the next 18 months, the construction schedule is worth planning around. That covers both what buyers will see from the shoreline and how you describe the finished waterfront that is on the way. Mary Lee & Associates can map a listing timeline against the city's published construction updates as they arrive. Schedule a free consultation.