The City of Sammamish's newest capital plan calls the SE 24th Street boardwalk "currently considered to be in generally good and serviceable condition." On Friday, October 30, the city closed one piece of it, section B, "indefinitely until it can be replaced," and permanently shut both of its entrances.
Section B will stay closed until it is replaced, and the replacement money is budgeted for 2027 and 2028. For anyone who walks this stretch of SE 24th Street, the new pathway beside the boardwalk is the route for at least the next year. The city council's November 17 public hearing is the next scheduled chance to comment on that timeline.
What changed on SE 24th Street last Friday
The city's closure notice is short. Section B is closed until it is replaced. Its east and west entrances are "permanently closed to public access going forward." A protected pedestrian pathway next to the boardwalk opened the same day it closed.
The notice also changes the rules for anyone on wheels. The city asks "that cyclists, including e-bike riders, dismount and walk their bikes or use the westbound lane as permitted by law." Anyone who rode this corridor on a bike or e-bike now has two choices: walk the bike beside the closed section or ride in the westbound lane.
The other three sections stay open. The city describes the boardwalk as "four elevated wood-framed structures supported by battered steel piles," and only section B is closed.
The paper trail, in order
The boardwalk has appeared in city planning documents for three years. Read in order, they show a small maintenance item becoming a funded rebuild:
| Date | City document | What it says about the boardwalk |
|---|---|---|
| September 2023 | Structural assessment, as summarized in later capital plans | Generally serviceable. Nonstructural issues: uneven decking, buckling handrail trim caps, wire-rope railing gaps over 4 inches, settlement near the concrete abutments |
| October 14, 2025 | Public Works 2025–2026 work plan presentation | "Unplanned: repair of SE 24th Street Boardwalk" listed among accomplishments. Preliminary engineering and design for rehabilitation planned for 2026 |
| November 6, 2025 | Bicycle and Pedestrian Mobility Plan | Boardwalk upgrade planned for the 2026–2031 transportation improvement plan. Recommends a two-way shared-use path on the north side |
| 2026–2031 capital plan | Project TR-139, new | $308,000 for design in 2026, construction and contingency in 2027 and 2028, $3.204 million total |
| Proposed 2027–2028 budget | TR-139 | $3,240,158 for alternatives analysis, design and construction, Q4 2026 through Q4 2028 |
| Proposed 2027–2032 capital plan | TR-139 | $3.240 million, anticipated start Q3 2027, anticipated end Q4 2030 |
| October 30, 2026 | Closure notice | Section B closed until replaced. Protected pathway installed alongside |
The 2026–2031 plan states the project's reason directly. It is an "Evaluation for Repair/Replacement to prevent boardwalk failure," and the plan notes that the listed issues "have required ongoing maintenance effort/costs from the Maintenance and Operations Center." The proposed 2027–2032 plan states the goals: improve pedestrian safety, reduce maintenance needs, and "preserve the useful life of the boardwalk."
The boardwalk was already on the city's maintenance list, and it already had a repair line in the 2025 work plan. With section B closed, it now has a fixed detour as well.
Where the money lands on the calendar
The funding table in the proposed 2027–2032 capital plan puts $503,000 in FY2027 from REET 2 and $2.737 million in FY2028 from the city's existing real estate excise tax fund balance. Nothing is listed for 2029 or later.
Most of the money arrives in 2028. The same page gives an anticipated end date of Q4 2030. The proposed 2027–2028 budget uses a shorter window, Q4 2026 through Q4 2028, for alternatives analysis, design and construction. Under either schedule, the permanent fix comes years from now. Any work that starts this winter would be study and design, not construction.
The Bicycle and Pedestrian Mobility Plan suggests what the replacement could look like. For SE 24th Street between Audubon Park Drive and 232nd Avenue SE, it recommends "a two-way shared-use path" along the north side of the street. The same document lists this corridor among projects that "did not rise to the top" of its top 10 priorities, and keeps it for future consideration as funding and priorities change. The capital plan describes rehabilitating the existing structures. The mobility plan describes a shared-use path. The alternatives analysis in the proposed budget is the step where the city chooses between them.
November 17 is the hearing still ahead
The city council holds public hearings on the proposed 2027/2028 biennial budget and the 2027 property tax levy on November 4 and November 17, 2026. Both meetings start at 6:30 p.m. The city's 2026 legal notices page also lists a hearing notice for the 2027–2032 six-year capital improvement plan on the same two dates.
With the November 4 hearing behind it, the council's November 17 meeting is the remaining scheduled hearing on the budget and capital plan that fund TR-139. The hearing notice has the meeting details. For residents who use the corridor, the questions are concrete:
- Whether the $503,000 planned for 2027 covers enough design work to keep construction funding in 2028
- Whether the alternatives analysis includes the north-side shared-use path from the mobility plan
- How long the protected pathway beside section B is expected to stay in place
Getting to the lakes this week
Until something is built, people walking this part of the plateau will keep using the closed section's pathway and the parks around it. Here are the city's details for the two lakeside parks nearby, plus other work that affects routes in the area through Friday.
Beaver Lake Park has a lake-side address of 25101 SE 24th Street and an athletic-field-side address of 2526 244th Avenue SE. The 83-acre park has forest trails, swimming access, a boat launch and fishing on Beaver Lake. On the field side are sports fields, a playground, a picnic shelter, an off-leash dog park and restrooms. Beaver Lake Lodge is available to reserve.
Pine Lake Park is at 2401 228th Ave SE. It is a 19-acre wooded park on the shore of Pine Lake, with a beach, a dock, trails, picnic shelters, play structures, restrooms, a basketball court, a sports field, boat launches, fishing and swimming.
Thursday evening at the Lodge: the city's free Creative Connect workshop runs Thursday, November 5, from 6:30 to 8 p.m. at the Lodge at Beaver Lake Park. Artist Shyamashree Acharya leads participants in making small books.
The city's October 30 Cone Zone update lists other work in the area through Friday, November 6:
- SE 32nd Street sidewalk work between 241st and 244th Avenues SE, 7 a.m. to 5 p.m., with alternating one-lane traffic and flaggers. Driveway access stays open.
- George Davis Creek work on East Lake Sammamish Parkway south of NE 7th Court, possibly including East Lake Sammamish Shore Lane, with intermittent single-lane traffic. The city points drivers to its detour map.
- Storm pipe camera inspections and cleaning at five locations, including 228th Avenue SE at SE 8th Street and NE 26th Place, with occasional single-lane closures.
The SE 32nd Street sidewalk crew finishes Friday. The SE 24th Street pathway has no end date yet, and the next budget hearing on its replacement is November 17.
Public works projects like this one shape how buyers see a property near the corridor, so pricing a listing nearby should account for them. Mary Lee & Associates tracks city capital plans and their timelines as part of preparing a home for sale. If you own near SE 24th Street and want to know how a multi-year project could affect your sale timing, schedule a free consultation.